Question No: 1    ( Marks: 1 )    - Please choose one

 ________ identifying which quality standards are relevant to the project and determining how to satisfy them.

 

       ► Quality Planning

       ► Communications Planning

       ► Organization Planning

       ► Staff Acquisition

   

Question No: 2    ( Marks: 1 )    - Please choose one

 These all are outputs of Initiating Process except

 

       ► Project Manager Assignments

       ► Constraints

       ► Selection Criteria 

       ► Assumptions

   

Question No: 3    ( Marks: 1 )    - Please choose one

 Project management processes can be organized into _____________ groups

 

       ► Four

       ► Five

       ► Six 

       ► Seven

  

Question No: 4    ( Marks: 1 )    - Please choose one

 Product quality depends on its conformance to ______

 

       ► Software requirements

       ► Development standards

       ► Implicit requirements 

       ► All of given

 

Question No: 5    ( Marks: 1 )    - Please choose one

 _______is the technical kernel of software engineering

 

       ► Design

       ► Implementation

       ► Requirements analysis

       ► Testing

    

Question No: 6    ( Marks: 1 )    - Please choose one

 Mode of specification has a great impact on quality of solution. Forcing SWE to work with incomplete, inconsistence, or misleading specifications result in frustration and confusion affecting:

 

       ► Quality

       ► Timeliness and

       ► Completeness of SW product

       ► All of given

 

   

Question No: 7    ( Marks: 1 )    - Please choose one

 Finally, the specification includes a ________

 

      ► Bibliography

       ► Appendix

       ► Both Bibliography and Appendix

       ► Reference

 

Question No: 8    ( Marks: 1 )    - Please choose one

 Cognitive model describes a system as perceived by its _________

 

       ► User community

       ► Developer

       ► Top level management 

       ► Manager

    

Question No: 9    ( Marks: 1 )    - Please choose one

 A review of the Software Requirements Specification is conducted by ________

 

       ► Software developer

       ► Customer

       ► Both the software developer and the customer

       ► Top level management

 

Question No: 10    ( Marks: 1 )    - Please choose one

 A meeting is conducted at a _________ and attended by both software engineers and customers.

 

       ► Software engineer site

       ► Neutral site

       ► Customer site 

       ► Company site

 

Question No: 11    ( Marks: 1 )    - Please choose one

 The model serves as the basis for the creation of ________ for the Software.

 

       ► Design

       ► Maintenance

       ► Testing 

       ► Specifications

 

Question No: 12    ( Marks: 1 )    - Please choose one

 Throughout evaluation and solution synthesis, the analyst's primary focus is on

       ► "What, not "how." 

       ► Model

       ► Evaluation and Synthesis

       ► Specification

 

Question No: 13    ( Marks: 1 )    - Please choose one

 In problem evaluation area of effort, once problems have been identified, the ___________determines what information is to be produced by the new system and what data will be provided to the system.

 

       ► Analyst

       ► Designer

       ► Coder

       ► Manager

 

Question No: 14    ( Marks: 1 )    - Please choose one

 Requirements are refined and analyzed to assess their clarity, completeness, and_______

 

       ► Correctness

       ► Consistency

       ► Concurrency 

       ► None of given

 

Question No: 15    ( Marks: 1 )    - Please choose one

 A software project that meets all the stated objectives is a success of _________

 

       ► Project quality

       ► Project fundamental purpose 

       ► Project management myth   @@@@

       ► Project requirement

 

Question No: 16    ( Marks: 1 )    - Please choose one

 All of the following describe the activity list except:

 

       ► It's an extension of the WBS

       ► It include all activities of the project

       ► It describe the WBS update

       ► It include a description of project activities

 

Question No: 17    ( Marks: 1 )    - Please choose one

Software project are carried out sequentially and that each phase is completed before the next is taken up.

       ► The Prototyping Model

       ► The Incremental Model

       ► The Waterfall model

       ► The Spiral model

   

Question No: 18    ( Marks: 1 )    - Please choose one

 Project management is a _________of constant communication and negotiation.

       ► Process

       ► Concept

       ► Practice

       ► None of given

 

   

Question No: 19    ( Marks: 1 )    - Please choose one

 These all are design phase activities except

       ► Output Design

       ► Input Design

       ► The software test plan

       ► Software Selection

 

   

Question No: 20    ( Marks: 1 )    - Please choose one

 Which organization has set the de facto standards for project management techniques?

 

       ► PMBOK

       ► PMI

       ► PMA

       ► PMO

 

   

Question No: 21    ( Marks: 2 )

 Give the name of configuration control tools?

 

Answer:

Automatic version control and

  • Change control tools
  • Monitoring, auditing and registration support utilities
  • Storage facilities; a safe repository for all approved configuration items, including:

        On-site storage for the day to day development process

        Off-site storage for catastrophe recovery

   

Question No: 22    ( Marks: 3 )

 Software requirements analysis a bridge between system engineering and software design, show it by diagram.

 

Requirements analysis

Requirements analysis is a software engineering task that bridges the gap

between system level requirements engineering and software design

(Figure 1). Requirements engineering activities result in the specification

of software's operational characteristics (function, data; and behavior),

indicate software's interface with other system elements, and establish

constraints that software must meet. Requirements analysis allows the

software engineer (sometimes called analyst in this. role) to refine the

software allocation and build models of the data, functional, and

behavioral domains that will be treated by software. Requirements

analysis provides the software designer with a representation of

information, function, and behavior that can be translated to data,

architectural, interface, and component-level designs. Finally, the

requirements specification provides the developer and the customer with

the means to assess quality once software is built.

Figure 1: a bridge between system engineering and software design

 

 

Question No: 23    ( Marks: 5 )

 Write down the software process player's names and their roles in projects.

 

Answer:

 

PM Process Groups

Project management processes can be organized into five groups of one or more

processes each:

1. Initiating processes—authorizing the project or phase

2. Planning processes—defining and refining objectives and selecting the best

of the alternative courses of action to attain the objectives that the project

was undertaken to address

3. Executing processes—coordinating people and other resources to carry out

the plan

4. Controlling processes—ensuring that project objectives are met by

monitoring and measuring progress regularly to identify variances from plan

so that corrective action can be taken when necessary

5. Closing processes—formalizing acceptance of the project or phase and

bringing it to an orderly end

Each process is described by:

– Inputs

– Tools & Techniques

– Outputs

   

Question No: 24    ( Marks: 10 )

 Explain the following terms regarding project characteristics and project dimensions.

·     Temporary,

·     Unique,

·     Aims,

·     People,

·     Process

 

Answer:

 

1. Temporary

Temporary means that every project has a definite beginning and a definite end.

The end is reached when the project's objectives have been achieved, or it

becomes clear that the project objectives will not or cannot be met, or the need for

the project no longer exists and the project is terminated. Temporary does not

necessarily mean short in duration; many projects last for several years. In every

case, however, the duration of a project is finite; projects are not ongoing efforts.

 

2. Unique,

Projects involve creating something that has not been done in exactly the same

way before and which is, therefore, unique and distinct

 

Aims/Tasks/Purpose

The projects are designed to achieve specific targets defined in terms of aims,

tasks or a purpose. The nature and size of the project depends upon

complexity of the task, realization of the aims and scope of the purpose any

organization wants to achieve. In short project has to be aimed for achieving

certain tasks in a given time frame.

 

People must be organized into effective teams, motivated to do high-quality

software work, and coordinated to achieve effective communication.

 

 

 

 