Question # 1 of 20 ( Start time: 08:38:23 PM ) Total Marks: 1

Which of the following refers to a narrative description of the work to be accomplished?

Select correct option:

            The statement of work (SOW)

            The project specifications

            The milestone schedule

            The work breakdown structure (WBS)

Question # 2 of 20 ( Start time: 08:40:08 PM ) Total Marks: 1

Which of the following statements is TRUE for Work breakdown Structure (WBS)?

Select correct option:

            Project Manager must structure work into small elements that are manageable

            Project Manager must structure work into small elements that are independent

            Project Manager must structure work into small elements that are measurable

            All of the given options

Question # 3 of 20 ( Start time: 08:41:38 PM ) Total Marks: 1

Scope of a project is the …………… total of all of a project's products and their requirements or features

Select correct option:

            Sum

            Product

            Sum and product

            None of the above

Question # 5 of 20 ( Start time: 08:44:56 PM ) Total Marks: 1

Which of the following life cycle phases includes brainstorming and common sense at planning stage?

Select correct option:

            Conceptualization

            Feasibility

            Preliminary planning

            Detail planning

Question # 6 of 20 ( Start time: 08:45:52 PM ) Total Marks: 1

Quality assurance is:

Select correct option:

            Detection based

            Inspection based

            Prevention based

            People based

Question # 7 of 20 ( Start time: 08:47:50 PM ) Total Marks: 1

The three general preconditions for achieving lasting success as a project manager are:

Select correct option:

            Technical Skills, Ability, Human Skills and Design Skill

            Ability, Motivation to manage and Opportunity

            Motivation to manage, Opportunity and Conceptual Skill

            Ability, Capacity and Supervision

Question # 8 of 20 ( Start time: 08:49:45 PM ) Total Marks: 1

Which of the following statements gives the Technical definition of Project Planning?

Select correct option:

            Working out of sub-components in some degree of detail

            To cover area of government legislation & regulation related to "use of resources"

            "Planned use of any /all resources"- Succession of five year plans

            Structured sequence of events leading to desired set of objectives

Question # 9 of 20 ( Start time: 08:51:41 PM ) Total Marks: 1

Which of the following require input from a large number of functional units and usually control vast resources?

Select correct option:

            Individual projects

            Staff projects

            Special projects

            Matrix or Aggregate projects

Question # 10 of 20 ( Start time: 08:52:40 PM )            Total Marks: 1

Which of the following is the responsibility of proposed project manager?

Select correct option:

            Project Plan & strategy

            Description of Project Organization

            Development of organizational Chart

            All of the given options

Question # 11 of 20 ( Start time: 08:53:04 PM )            Total Marks: 1

Which of the following is the discount rate that equates the present values of the two sets of flows?

Select correct option:

            Discounted Cash Flow

            Pay Back Period

            Discounted Cash Flow

            Internal Rate of Return

Question # 12 of 20 ( Start time: 08:54:56 PM )            Total Marks: 1

Which of the following items involves the quantitative aspects of planning?

Select correct option:

            Budget development

            Project administration

            Leadership styles

            Conflict management

Question # 13 of 20 ( Start time: 08:56:51 PM )            Total Marks: 1

The main purpose of a _______________ is to function as a blueprint for the group's business operations.

Select correct option:

            Business Plan

            Scope statement

            Feasibility Study

            Work Breakdown Structure

Question # 14 of 20 ( Start time: 08:57:43 PM )            Total Marks: 1

___________ is the lowest level of quality development.

Select correct option:

            Quality Assurance

            Quality Management

            Inspection

            Total Quality Management

Question # 15 of 20 ( Start time: 08:59:20 PM )            Total Marks: 1

Fredrick Taylor- Father of Scientific Management was a _______________

Select correct option:

            Mechanical Engineer

            Chemical Engineer

            Technical Engineer

            Electrical Engineer

Question # 16 of 20 ( Start time: 09:00:40 PM )            Total Marks: 1

Fitness to cost can be obtained by:

Select correct option:

            Determining the customer's needs

            Building of customer needed products

            Obtaining high quality and low cost products

            Developing quality management

Question # 17 of 20 ( Start time: 09:02:29 PM )            Total Marks: 1

All of the following are relevant factors of competitive bids EXCEPT:

Select correct option:

            Schedule

            Financial Stability

            Financing Offer

            Ease of minor changes adopted

Question # 18 of 20 ( Start time: 09:04:21 PM )            Total Marks: 1

The emphasis is changed from product to process at ______________ stage.

Select correct option:

            Inspection

            Quality control

            Quality management

            Quality assurance

Question # 19 of 20 ( Start time: 09:06:21 PM )            Total Marks: 1

Quality is defined by_____________.

Select correct option:

            Customer

            Proposal manager

            Higher management

            Quality management

--
--
Please visit www.vuzs.net For Current & Old Papers, Quizzes, Assignments and study material.
 
To post a new message on this group, send email to vuZs@googlegroups.com
 
Message Posting Rules: http://vuzs.net/faq/4795-vuzs-google-groups-basic-rules-for-posting-messages.html
--
To unsubscribe from this group, send email to vuZs+unsubscribe@googlegroups.com
--
To join this group Send blank email to vuZs+subscribe@googlegroups.com
or visit
http://groups.google.com/group/vuZs/subscribe

--
--
Please visit www.vuzs.net For Current & Old Papers, Quizzes, Assignments and study material.
 
To post a new message on this group, send email to vuZs@googlegroups.com
 
Message Posting Rules: http://vuzs.net/faq/4795-vuzs-google-groups-basic-rules-for-posting-messages.html
--
To unsubscribe from this group, send email to vuZs+unsubscribe@googlegroups.com
--
To join this group Send blank email to vuZs+subscribe@googlegroups.com
or visit
http://groups.google.com/group/vuZs/subscribe

No comments:

Post a Comment