Question # 1 of 20 ( Start time: 08:38:23 PM ) Total Marks: 1
Which of the following refers to a narrative description of the work to be accomplished?
Select correct option:
The statement of work (SOW)
The project specifications
The milestone schedule
The work breakdown structure (WBS)
Question # 2 of 20 ( Start time: 08:40:08 PM ) Total Marks: 1
Which of the following statements is TRUE for Work breakdown Structure (WBS)?
Select correct option:
Project Manager must structure work into small elements that are manageable
Project Manager must structure work into small elements that are independent
Project Manager must structure work into small elements that are measurable
All of the given options
Question # 3 of 20 ( Start time: 08:41:38 PM ) Total Marks: 1
Scope of a project is the …………… total of all of a project's products and their requirements or features
Select correct option:
Sum
Product
Sum and product
None of the above
Question # 5 of 20 ( Start time: 08:44:56 PM ) Total Marks: 1
Which of the following life cycle phases includes brainstorming and common sense at planning stage?
Select correct option:
Conceptualization
Feasibility
Preliminary planning
Detail planning
Question # 6 of 20 ( Start time: 08:45:52 PM ) Total Marks: 1
Quality assurance is:
Select correct option:
Detection based
Inspection based
Prevention based
People based
Question # 7 of 20 ( Start time: 08:47:50 PM ) Total Marks: 1
The three general preconditions for achieving lasting success as a project manager are:
Select correct option:
Technical Skills, Ability, Human Skills and Design Skill
Ability, Motivation to manage and Opportunity
Motivation to manage, Opportunity and Conceptual Skill
Ability, Capacity and Supervision
Question # 8 of 20 ( Start time: 08:49:45 PM ) Total Marks: 1
Which of the following statements gives the Technical definition of Project Planning?
Select correct option:
Working out of sub-components in some degree of detail
To cover area of government legislation & regulation related to "use of resources"
"Planned use of any /all resources"- Succession of five year plans
Structured sequence of events leading to desired set of objectives
Question # 9 of 20 ( Start time: 08:51:41 PM ) Total Marks: 1
Which of the following require input from a large number of functional units and usually control vast resources?
Select correct option:
Individual projects
Staff projects
Special projects
Matrix or Aggregate projects
Question # 10 of 20 ( Start time: 08:52:40 PM ) Total Marks: 1
Which of the following is the responsibility of proposed project manager?
Select correct option:
Project Plan & strategy
Description of Project Organization
Development of organizational Chart
All of the given options
Question # 11 of 20 ( Start time: 08:53:04 PM ) Total Marks: 1
Which of the following is the discount rate that equates the present values of the two sets of flows?
Select correct option:
Discounted Cash Flow
Pay Back Period
Discounted Cash Flow
Internal Rate of Return
Question # 12 of 20 ( Start time: 08:54:56 PM ) Total Marks: 1
Which of the following items involves the quantitative aspects of planning?
Select correct option:
Budget development
Project administration
Leadership styles
Conflict management
Question # 13 of 20 ( Start time: 08:56:51 PM ) Total Marks: 1
The main purpose of a _______________ is to function as a blueprint for the group's business operations.
Select correct option:
Business Plan
Scope statement
Feasibility Study
Work Breakdown Structure
Question # 14 of 20 ( Start time: 08:57:43 PM ) Total Marks: 1
___________ is the lowest level of quality development.
Select correct option:
Quality Assurance
Quality Management
Inspection
Total Quality Management
Question # 15 of 20 ( Start time: 08:59:20 PM ) Total Marks: 1
Fredrick Taylor- Father of Scientific Management was a _______________
Select correct option:
Mechanical Engineer
Chemical Engineer
Technical Engineer
Electrical Engineer
Question # 16 of 20 ( Start time: 09:00:40 PM ) Total Marks: 1
Fitness to cost can be obtained by:
Select correct option:
Determining the customer's needs
Building of customer needed products
Obtaining high quality and low cost products
Developing quality management
Question # 17 of 20 ( Start time: 09:02:29 PM ) Total Marks: 1
All of the following are relevant factors of competitive bids EXCEPT:
Select correct option:
Schedule
Financial Stability
Financing Offer
Ease of minor changes adopted
Question # 18 of 20 ( Start time: 09:04:21 PM ) Total Marks: 1
The emphasis is changed from product to process at ______________ stage.
Select correct option:
Inspection
Quality control
Quality management
Quality assurance
Question # 19 of 20 ( Start time: 09:06:21 PM ) Total Marks: 1
Quality is defined by_____________.
Select correct option:
Customer
Proposal manager
Higher management
Quality management
----
Please visit www.vuzs.net For Current & Old Papers, Quizzes, Assignments and study material.
To post a new message on this group, send email to vuZs@googlegroups.com
Message Posting Rules: http://vuzs.net/faq/4795-vuzs-google-groups-basic-rules-for-posting-messages.html
--
To unsubscribe from this group, send email to vuZs+unsubscribe@googlegroups.com
--
To join this group Send blank email to vuZs+subscribe@googlegroups.com
or visit
http://groups.google.com/group/vuZs/subscribe
No comments:
Post a Comment